Project Construction Plan Assignment
Complete this assignment to form part of your portfolio.
In your own words describe the steps involved and tools / equipment required for the project
Name
Ricky aurisch
Date
3/12/08
Project
name
Install window frames
Construction steps
How it happens
Tools and Equipment required
1
We collected a pre made frame and window frame which we lined with with brown paper to represent sisalation
tape
2
Then we fixed 4 pieces of weather board on each corner to determine how far the window frame must protrude the frame the check for plumb and squareness
Hammer, nails, square
3
Remove the weather board and line the out side with alcor the weather board all the way round the window
Hammers, nails
4
Spin the frame around and place thin lengths of mdf around the frame to act as the gyprock
Hammer, nails
5
Place your sill in check out both ends allowing 80mm over hang for the acatrave to sit on then router the edges and lightly sand
Square, nail gun, sanding paper
6
Cut and sand some chocks the fit down the inside of the 2 sides then 1 across the top fix them all in
Mitre saw, thicknesser, nail gun
7
The all you have to do is mitre some lengths of arcatrave allowing 10 mm all the way round the fix doneeee.
Square, nail gun